Electrical Measurement, Testing and Controls




Businesses in power and the source of almost all the crop production process and the use of equipment is important source of danger with the same rate.

running machine with electricity, equipment and leakage can occur for various reasons of security measures taken as a result of current and voltage equipment may jeopardize the life and property safety .

For example, the grounding process , a case of this kind of error that can occur is one of the actions to be implemented in order to protect human life. The device housing is grounded in accordance with the regulations , if necessary, additional devices such as leakage relay risks associated with electricity can be reduced if the electrical system safety is increased.

of electrical installations and systems can be used safely and continuous , periodic inspection and testing of electrical equipment and installations in order to detect a variety of errors and defects that may occur in a timely manner should be made.

must periodically check the Use of Work Equipment Regulations Health and Safety Conditions in Annex III section 2.3 of the Electrical Equipment and Installation 2. Subject to Control periodically under the Business Equipment substance. subparagraph ( Installation ), and are set forth in subparagraph .

UZMAN MUAYENE VE GOZETIM, Electrical Engineer qualified controllers in the site precise and calibrated measurement tools, carries out independent and credible 3rd party engineering controls providing periodic measurement and control of accredited inspection bodies serve as the first to the highest standards of business used in your electrical installations and equipment.

UZMAN MUAYENE VE GOZETIM, Electrical Engineer qualified controllers in the site precise and calibrated measurement tools, carries out independent and credible 3rd party engineering controls providing periodic measurement and control of accredited inspection bodies serve as the first to the highest standards of electrical equipment and systems used in your business.

ELECTRICAL EQUIPMENT AND EQUIPMENT HELD BY NATURAL CONTROL UZMAN MUAYENE VE GOZETIM PERIODIC CHECKS

 

  • Electrical Installation Compliance Report
  • Measurement of Strong Flow Installations
  • Measurement of Lighting Installations
  • Body Protection Ground
  • Operation Ground And Clipboard
  • Explosive Atmospheres Electrical Testing
  • Generator Testing And Controls
  • Accumulators , Transformers Tests
  • Grounding: Grounding systems of measurement and control , body protective earthing
  • Lightning protection systems of measurement and control
  • Cathodic Protection
  • Electric panel

Table 3 Electrical Equipment and Installation of Control Period and Minimum Criteria

NAME OF EQUIPMENT CONTROL PERIOD PERIODIC CONTROL MEASURES
( Maximum Time ) (The relevant standards are listed below. )
Electrical Installation, Grounding Installation , Lightning Period specified in the standard 1 year Official Gazette dated 21.08.2001 and numbered 24500 Ground Regulations published in Electrical Installations , dated 30.11.2000 and published in the Official Gazette No. 24 246 Electrical Power Plants Directive , dated 04/11/1984 and the Official Gazette No. 18565 ' published in the TSE Regulation on Internal Electrical Installations are performed according to the matters specified in the EN 60079 standard .
Accumulators , Transformers 1 year It is carried out under the conditions determined by the manufacturer